Brad's Car Manuals: A 3rd party mirror of CHARM + LEMON car manuals
Home >> Porsche >> 1979 >> 930 >> Labor Times >> Engine Mechanical >> Mechanical >> Valve >> Grind Complete

Grind Complete

Download the full database via torrent (~1.1 TB)
Includes: Remove carbon, check surfaces for warpage, reface or replace Valves, resurface Valve Seats and clean Valve Guides. Adjust Valves (where applicable).

Applies ToNoteStandard HoursWarranty HoursSkill Level
H6, Both31.1A
H6, Left23.3A
H6, Right Side21.7A
Additional Procedure: VALVE: Grind Complete:
Where Air Cond interferes add0.4A
Combination Procedure: VALVE GUIDE: Remove & Replace:
H6, All1.5A
H6, Each0.5A